Toll processing agreements: what to specify
A toll processing agreement is useful when a company owns raw materials and has a market for the finished product, but for some reason does not have its own grinding, blending or packing line. The raw materials and finished products remain the customer’s property throughout the process. The processor performs the agreed work for a previously agreed fee and returns the finished product. Most disputes arise from figures that the parties failed to agree beforehand: how much finished product should be obtained, what percentage of losses is acceptable and what should happen to waste. The legal framework discussed below is that of the Russian Federation.
How does toll processing work?
The customer supplies its raw materials to the processor, who performs the work and returns the result. Ownership of both the raw materials and finished products remains with the customer; the processor receives payment only for the work performed.
Legally, this is a contract for work. Under Article 702 of the Civil Code of the Russian Federation, the contractor undertakes to perform specified work in accordance with the customer’s instructions and deliver the result, while the customer undertakes to accept and pay for it. Business communications often describe processing as a service, but the applicable rules are those governing contracts for work in Chapter 37 of the Civil Code.
The use of customer-supplied materials must be stated in the agreement. By default, Article 704 of the Civil Code provides for work to be performed using the contractor’s own resources, including its own materials, unless otherwise agreed.
Ownership is addressed in Article 220 of the Civil Code on processing: unless otherwise provided in the agreement, ownership of a new item made from another party’s materials belongs to the owner of those materials. Collagen protein made from the customer’s hides, or a blend made from its ingredients, therefore belongs to the customer even when the finished product looks completely different from the raw materials.
Who is responsible for raw materials while they are with the processor?
The processor is responsible for safeguarding them; as a general rule, the customer bears the risk of accidental loss. The allocation of risks can be changed by agreement and should be settled when the contract is signed, rather than after a batch has been damaged.
- Article 714 of the Civil Code: the contractor is responsible for failure to safeguard materials and items supplied for processing that are in its possession in connection with the contract.
- Article 705 of the Civil Code: the risk of accidental loss or damage to property supplied for processing is borne by the party that supplied it, unless otherwise provided by law or agreement. The contractor bears the risk of accidental loss of the result until the customer accepts it. If delivery or acceptance is delayed, the risk passes to the party responsible for the delay.
- Article 713 of the Civil Code specifically concerns work performed using the customer’s materials. The contractor must use the materials economically and prudently, report on their use after completing the work and return any remainder, or—with the customer’s agreement—reduce the price of the work by the value of the remainder. If the result could not be achieved because of defects in the materials, the contractor may claim payment only if it proves that those defects could not have been identified during proper acceptance procedures.
- Article 716 of the Civil Code: if the contractor discovers that materials are unsuitable or defective, it must immediately notify the customer and suspend work pending instructions.
Articles 713 and 716 lead to a practical conclusion: incoming inspection benefits both parties. The more clearly the raw material acceptance procedure is described, the easier it is to establish why a result did not meet expectations.
What should the agreement specify?
In addition to price and timing, the agreement should include a technical specification, expected yield and loss allowances, procedures for accepting raw materials and finished products, and arrangements for waste and unused materials. The following terms often raise questions.
| Term | What to record | Why it matters |
|---|---|---|
| Technical specification | The required result: particle size distribution, moisture content, blend formula, packaging and labelling | The result can only be verified against parameters recorded beforehand |
| Expected yield | The quantity of finished product expected per unit of raw material and how it is calculated | Provides the basis for the material usage report under Article 713 of the Civil Code |
| Process losses | The allowable percentage of losses—dust, material retained in equipment, moisture evaporation—and the measurement method | Without an allowance, any shortfall can become a dispute |
| Waste and unused materials | Whether they are returned to the customer, disposed of or purchased; who pays for disposal | As a general rule, waste from customer-supplied materials also belongs to the customer |
| Raw material acceptance | Weighing, sampling, packaging inspection, the deadline for reporting non-conformity and the form of the acceptance record | Records the condition in which the raw materials were received |
| Timing | Start and completion dates, linked to receipt of raw materials and documentation | The processor cannot start without raw materials and accompanying documents |
| Finished product acceptance | Who accepts the finished product, where and within what period, and which parameters are checked | Under Article 720 of the Civil Code, a customer who accepts work without checking it loses the right to rely on obvious defects |
| Return of finished products | Collection or delivery, the collection deadline and storage charges after that deadline | Determines when risks pass to the customer |
Expected yields and loss allowances are best confirmed by a trial run on a small batch. They differ for grinding caked powders, blending and producing protein from animal-derived raw materials, so there is no universal figure. Under Article 720 of the Civil Code, an expert examination may be appointed at either party’s request in a dispute over defects, making it useful to agree measurement methods beforehand.
Termination should be discussed separately. In certain termination situations, Article 728 of the Civil Code requires the contractor to return the materials and items supplied for processing or, if that is impossible, compensate the customer for their value.
What documents accompany raw materials and finished products?
On receipt, documents are needed to record the transfer of raw materials and confirm their quality. On completion, the documents include a work completion certificate, processing report and finished product documentation. Animal-derived raw materials also require veterinary accompanying documents.
When raw materials are supplied:
- the agreement and its appendices: technical specification, expected yields and loss allowances;
- a delivery note or transfer and acceptance record for raw materials supplied for processing, stating the description, quantity and contractual value;
- the manufacturer’s or supplier’s documents confirming the quality and safety of the materials: specification, certificates of analysis and declaration of conformity where required for the product type;
- for animal-derived raw materials: a veterinary accompanying document in Russia’s federal state information system, FGIS “Mercury”.
When finished products are returned:
- a work completion certificate;
- a processing report stating the raw material quantity used, finished product quantity, actual losses, unused materials and waste;
- a delivery note for the return of finished products and unused raw materials;
- quality control results for the parameters specified in the technical specification;
- for animal-derived products: a veterinary accompanying document for the finished products.
How are toll processing materials treated in accounting and taxation?
The processor does not purchase the raw materials or recognise them on its balance sheet: they are recorded in off-balance-sheet account 003. The processor’s revenue is the price of its work rather than the value of the raw materials.
Under the Russian Chart of Accounts (Ministry of Finance Order No. 94n of 31 October 2000), account 003, “Materials Accepted for Processing”, is intended for customer-owned raw materials for which the manufacturing organisation does not pay. They are recorded at the prices set in the agreements, with analytical records maintained by customer, raw material type and storage location. The practical rule is to state the raw material value in the agreement or delivery note even when no payment is made for it.
For Russian tax accounting, Article 39 of the Tax Code is a key provision: a sale includes a transfer of ownership of goods or the results of completed work for consideration, or the provision of services for consideration. Supplying toll processing materials does not transfer ownership and is therefore not treated as a sale of the raw materials. The processor sells its work. The VAT treatment and other taxes applicable to a particular situation should be checked with an accountant.
Frequently asked questions
How does toll processing differ from buying a finished product?
In a purchase, ownership passes to the buyer with the goods. In toll processing, the customer owns the raw materials from the outset and remains the owner of the finished products, paying only for processing.
Who owns processing waste?
As a general rule, the customer owns it because it comes from its raw materials. The agreement determines whether it is returned, disposed of or transferred to the processor.
Can products be made under the customer’s brand?
Yes, this is common in toll processing. Labelling, packaging and documentation for customer-branded products are described in the technical specification.
What yields should be specified in the first agreement?
They are best established by a trial run on a small batch. Figures for the particular raw material are discussed following an enquiry.
If you plan to supply raw materials for processing, describe the task in your processing enquiry. We will discuss the agreement’s terms and acceptance procedures.
Sources
- Civil Code of the Russian Federation, Article 702, “Contract for Work”: consultant.ru
- Civil Code of the Russian Federation, Article 704, “Work Performed Using the Contractor’s Resources”: consultant.ru
- Civil Code of the Russian Federation, Article 705, “Allocation of Risks Between the Parties”: consultant.ru
- Civil Code of the Russian Federation, Article 713, “Work Using the Customer’s Materials”: consultant.ru
- Civil Code of the Russian Federation, Article 714, “The Contractor’s Liability for Failure to Safeguard Property Supplied by the Customer”: consultant.ru
- Civil Code of the Russian Federation, Article 716, “Circumstances of Which the Contractor Must Notify the Customer”: consultant.ru
- Civil Code of the Russian Federation, Article 720, “Acceptance by the Customer of the Contractor’s Work”: consultant.ru
- Civil Code of the Russian Federation, Article 728, “Return by the Contractor of Property Supplied by the Customer”: consultant.ru
- Civil Code of the Russian Federation, Article 220, “Processing”: consultant.ru
- Tax Code of the Russian Federation, Article 39, “Sale of Goods, Work or Services”: consultant.ru
- Russian Chart of Accounts (Ministry of Finance Order No. 94n), account 003, “Materials Accepted for Processing”: consultant.ru